Route 13 Widening Project: Branson West to Kimberling City – update

 

Update for Week of Feb. 6-10, 2012

Work scheduled:

  • Grading rock and dirt along shoulders in Kimberling City
  • Installing traffic signal equipment at Route OO
  • Grading rock for relocated portion of Route 13 west of Stoneridge
  • Pouring concrete for bridge components for new bridge at south edge of
  • Bridge girders delayed until mid-to-late February for new bridge at south edge of Stoneridge

[adsenseyu1]
Traffic Impacts:

  • Lane closings on Route 13 between Bluebird Drive and Cove Street. Work hours: 9 a.m. to 3 p.m.
  • Short-term traffic stops at Route OO to allow equipment to enter and leave work areas
  • Trucks entering and leaving work areas using Stoneridge Center Road
  • Large equipment entering and leaving work areas
  • Work zone speed limit: 35 mph

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Widen Route 13 to four lanes between Branson West and Joe Bald/James River Road
  • Relocate a one-mile section of Route 13 through Stoneridge
  • Install new traffic signals at Route 13 and Business 13 at the south edge of Branson West
  • Build right-turn and left-turn lanes in various locations
  • Build two new bridges
    – Route 13 at the south edge of Stoneridge
    – Armadillo Lane over new Route 13 at Stoneridge
  • Resurface existing Route 13 through Stoneridge business district
  • Resurface Route 13 between Joe Bald/James River Road and the Kimberling City bridge
  • Prime contractor: Journagan Construction of Springfield
  • Project cost: $11.5 million

Scheduled completion: December 2012

Follow Me on Pinterest
Print Friendly

Leave a Reply

Powered by WP Robot

 

Add your comments to our stories and be entered into our random drawing to win this brand new tablet!


The more comments you leave, the better your chances of winning!
Contest ends July 30, 2012

Follow Me on Pinterest
Print Friendly